Installation of the steam turbine at KenGen Olkaria 1. It is the component that is usually rotated to drive the generator that produces electricity.
Installation of the steam turbine at KenGen Olkaria 1 AU 6 geothermal power plant . It is the component that is usually rotated to drive the generator that produces electricity.
Share

Leading energy producer, Kenya Electricity Generating Company PLC (KenGen) has started installing a Steam Turbine into the Olkaria 1 AU 6 Power Plant,  signalling a major breakthrough in the on-going construction of the power plant.

This is a great achievement, given that the Steam Turbine is the heart of the power plant. It is the component that is usually rotated to drive the generator that produces electricity.

KenGen Managing Director and CEO, Mrs, Rebecca Miano said the installation of the turbine’s lower casing starts today, Thursday 10th June 2021.

“This is the largest single unit of turbine we will be installing in any of our power plants with a capacity of 83.3MW and with its installation we are now entering the final phase of construction of the power plant,” Mrs. Miano said.

She further revealed that this was the first time a Fuji Turbine was being installed not only in Kenya but in Africa.

Fuji Electric which is the Turbine Manufacturer has deployed a Technical Adviser who will oversee the whole installation process and ensure success. He will be assisted by a team of Engineers from both Fuji Electric and KenGen.

READ>>>>>KenGen Begins Drilling Ksh7.6B Ethiopia Geothermal Wells [PHOTOS]

The turbine installation and its auxiliaries will take approximately three (3) months including dynamic balancing. This Installation will run alongside other major installations such as Generator Step Up Transformer (GSUT), Auxiliary transformers, MV and LV Switchgears, Non Condensable Gas extraction system, Cooling water system, Air Compressor system, Heating and Ventilation system and Emergency Diesel Generator.

Mrs. Miano said KenGen is happy with the progress of the project as it is on schedule despite challenges brought about by the COVID-19 pandemic. “With these activities running concurrently, it will ensure that the power plant’s commissioning is achieved in the last quarter of the year 2021,” she added.

In January this year, a team of 15 engineers and experts in heavy lifting successfully mounted a generator weighing 99 tonnes (99,000 kilograms) onto the power plant’s  Steam Turbine in Olkaria, Naivasha. Upon completion, the power plant will generate 83.3MW of electricity which will be injected into the national grid.

The generator which is worth Ksh 600 million was manufactured by Fuji Electric of Japan. It took five days to transport it from Mombasa to Olkaria with several stops along the way owing to its size.

Construction of Olkaria 1 AU 6 geothermal power plant started in December 2018 following a ground-breaking ceremony which was graced by President Uhuru Kenyatta.

The construction of the additional power plant is aligned to the company’s long-term strategy and the Least Cost Power Development Plan (LCPDP) focused on sustainable supply of renewable energy in support of the Government Big Four Agenda.

Currently, KenGen supplies about 72% of the electricity consumed in Kenya, with over 80% of this coming from renewable sources. The company has a total installed generation capacity of 1,818MW comprising hydro (826MW) geothermal (713MW) thermal (254MW) and wind (26MW).

READ>>>>>KenGen Banks Ksh440 Million from Ethiopia Drilling Deal

Written by
BUSINESS TODAY -

editor [at] businesstoday.co.ke

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Follow Us

Related Articles
Kakuzi Avocado bonus
BUSINESS

Smallholder Farmers Get Ksh10 Million Avocado Bonus

Smallholder Hass Avocado farmers affiliated with listed agri-business firm Kakuzi PLC are...

KBA CEO Raimond Molenje
BUSINESSLEADERSHIP

Raimond Molenje Confirmed KBA CEO After Acting for 9 Months

The Kenya Bankers Association (KBA) has announced the appointment of Raimond Molenje...

Dr Peter Ndegwa and Friends Golf Tournament - Beatrice Soy
BUSINESSSPORTS

Muthaiga Lady Wins Unique Golf Tournament Organised by Safaricom CEO

Beatrice Soy was the overall winner of the inaugural Dr Peter Ndegwa...

Citing Safety, Air Tanzania Is Banned Within the European Union
BUSINESSNEWS

Citing Safety, Air Tanzania Is Banned Within the European Union

The European Commission has barred Air Tanzania from flying to or within...