Fresh Trouble for Ruto as Kenya Faces Ksh44B Adani Termination Bill

Share
File image of President William Ruto
File image of President William Ruto
Share

Kenya could face a Ksh 44 billion termination bill from the controversial electricity transmission agreement with India’s Adani Group, nearly two years after President William Ruto announced that his administration had cancelled the deal.

Fresh disclosures from the National Treasury show that the government had not completed the contractual termination process by June 2026, despite the presidential announcement made in November 2024.

The figures are contained in the Fifth Annual Report on the State of Public-Private Partnerships (PPPs) in Kenya for the 2025/2026 financial year, published by the PPP Directorate on November 16, 2026.

According to the report, the estimated termination payment for the two electricity transmission projects stood at Sh43.943 billion, approximately Ksh 44 billion, as of June 2026.

The amount is higher than the projects’ combined estimated development cost of Ksh 40.49 billion, raising questions about the financial obligations attached to ending the agreements before the completion of their proposed 30-year operating period.

The report lists the projects as being at the commercial close stage, meaning the agreements had reached the stage where the contractual arrangements were concluded.

It also confirms that the termination process, which began during the 2024/2025 financial year, remained incomplete at the end of June 2026.

“However, the termination of the contract between KETRACO and Adani for the Transmission Lines project, which commenced in FY 2024/25, was still ongoing as at the end of FY 2025/26,” the report states.

The two projects involved the construction of a 400-kilovolt Lessos–Loosuk transmission line and a 220-kilovolt Kisumu (Kibos)–Kakamega–Musaga line.

They were intended to strengthen electricity transmission capacity and improve the movement of power across different parts of the country. The arrangement also included financing, construction, operation and maintenance of the infrastructure by the private investor over 30 years.

The wider Sh95.68 billion agreement covered three transmission lines measuring approximately 371 kilometres and three substations. One of the proposed lines was the 206-kilometre 400kV Gilgil–Thika–Malaa–Konza route.

Under the arrangement, Adani was expected to finance the construction and recover its investment through payments linked to the use of the transmission infrastructure.

Ruto announced cancellation in November 2024

The agreement came under intense public scrutiny in 2024 as Kenyans questioned the involvement of the Indian conglomerate in strategic national infrastructure.

On November 21, 2024, President Ruto announced that his government had initiated the cancellation of the electricity transmission agreement alongside a separate proposal by Adani to expand and operate Jomo Kenyatta International Airport (JKIA).

The announcement followed public opposition and legal challenges surrounding the two proposals.

The President’s announcement was expected to end the government’s involvement with the company in the two major infrastructure arrangements. However, subsequent developments showed that cancelling the agreements required more than a public declaration.

In June 2026, the High Court proceedings revealed that the government had not filed evidence demonstrating that the KETRACO-Adani contract had been formally cancelled.

The disclosure emerged during a case filed by the Law Society of Kenya against KETRACO and six other respondents at the Milimani Law Courts.

State Counsel informed the court that evidence of the formal cancellation had not been filed. The court also allowed Gitson Energy Limited to join the proceedings as an interested party.

The latest Treasury report now provides another indication of the difficulties surrounding the termination process, showing that it was still ongoing at the end of the 2025/2026 financial year.

Government’s wider PPP financial exposure

The Ksh 44 billion estimate also forms part of a much larger financial exposure arising from public-private partnership agreements across the country.

The Treasury report identifies 12 PPP projects with combined estimated termination payments of Sh400.34 billion as of June 2026.

These include the Nairobi Expressway, road construction projects, geothermal power plants, military housing and the Galana Kulalu food security project.

However, the Treasury clarified that the Sh400.34 billion does not represent an immediate government payment. The actual likelihood, value and timing of termination payments depend on individual contractual circumstances.

Using a World Bank-recommended termination probability of six per cent, the report places the maximum contingent liability for the projects at approximately Ksh 24 billion.

For the Adani electricity transmission agreement, the estimated Ksh 43.943 billion termination payment remains a major figure as the government works to conclude the contractual separation.

The report does not establish that the government has already paid Adani the money or that the company has received a final settlement. It provides an estimate of the financial exposure associated with terminating the agreements.

The government is therefore yet to conclude the process it announced in November 2024, leaving the final contractual and financial obligations surrounding the controversial electricity project unresolved.

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

PAST ARTICLES AND INSIGHTS

Related Articles
Nithi Bridge
NEWS

Nithi Bridge: The Multibillion Project Seking to End Decades of Road Tragedies

For decades, the Nithi Bridge along the Makutano–Embu–Meru Highway has been associated...

ELECTION WATCHNEWS

Sifuna in the US: Strategic Masterstroke or Just Hot Air?

Nairobi Senator Edwin Sifuna has taken the United States (US) by storm,...

This ad closes in 15 seconds