High Court Makes Landmark Ruling on Property Completion Delays

Share
offplan houses kenya
Developers who fail to deliver on their promises could face severe financial repercussions. (Photo: thisoldhouse.com)
Share

On 25 February 2025, the Kenya High Court has issued an important ruling regarding an off-plan property dispute. This ruling sheds light on the legal consequences of delayed completions, defects and failure to hand over possession by a property developer. The court’s decision makes it clear: developers who fail to deliver on their promises could face severe financial repercussions.

In this particular case, the purchaser entered into an agreement for sale, with the developer stipulating that the development project would be complete either 15 days after the issuance of a completion certificate by the developer’s architect or at the latest by 30 April 2015.

Despite paying the entire purchase price, the developer failed to meet the agreed-upon completion date and additionally left the property riddled with defects when it was finally handed over to the purchaser. To make matters worse, the developer’s agents delayed handing over the property, even after a formal completion notice was issued by the purchaser.
The Court found that the purchaser had fulfilled their obligations under the sale agreement and that the developer had breached its obligations under the agreement.

The Court held that the purchaser was entitled to: a refund of the entire purchase price with interest; a refund of monies spent on attending to the defects in the property; payment for loss of income on a monthly basis; and costs of the suit.

According to Cornelius Kigera and Alex Njage, who are Partners at Bowmans Kenya, the ruling serves as a clear reminder and warning to developers: that meeting deadlines and delivering quality properties is an enforceable obligation.

“For a long time, developers have treated timelines in sale agreements as a moveable target,” they said. “To deal with unavoidable delays, developers should ensure that their sale agreements include provisions for extensions of time and ensure to set clear expectations with their buyers.”

> Former Harambee Stars Goalkeeper Embroiled in Match-Fixing Scandal

> Top CEOs on Why they Are Optimistic About the Economy 

Written by
BT Correspondent -

editor [at] businesstoday.co.ke

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

PAST ARTICLES AND INSIGHTS

Related Articles
Justina Wamae
BUSINESS

Justina Wamae Faults High Costs, Taxes and Counterfeits for Diageo’s Exit from EABL

Former 2022 presidential running mate Justina Wamae has weighed in on Diageo’s...

NSE Chief Executive Officer Frank Mwiti at a past event. PHOTO/@NSE_PLC/X
BUSINESS

NSE Halts EABL Trading After Release of Market-Sensitive Information

The Nairobi Securities Exchange Plc (NSE) on Wednesday temporarily halted trading in...

CBK is seeking for KSh 60 billion in January 2026 for budget spending
FEATURED STORY

CBK to Raise KSh60Bn for Budgetary Spending in January 2026

CBK (Central Bank of Kenya) has gone into the primary bond market,...

Diageo exit was apparent even as EABL is building its war chest with a KSh 20 bn Cash Call
FEATURED STORY

 Diageo UK Plc Finally Exits East Africa’s Beer Market

Diageo Plc UK, a global brewing giant has sold its entire stake...